M City Condos Official Website | M6. Register Now

Watch history in the making

Mississauga’s most ambitious development is under construction starting with M1, M2, M3, and M4. M City is set to change the downtown Mississauga landscape forever, and this page will keep you informed with periodic construction updates, progress photos, video content and more. Be sure to check back for the latest onsite activity as these landmark buildings take shape.

PROGRESS UPDATES

If you'd like to catch up on the latest construction updates at M City or have questions or concerns, please feel free to contact us at info@mcitycondos.com or 905.232.0552.

Fall 2023

M5:

  • Shoring complete and excavation is well underway; complete to P3

M4:

  • Detailed excavation at footings is 80% complete, all that remains is the foundation under the ramp, which is currently being excavated and hauled from the site
  • We are starting to make our way back to grade with our first suspended parking slab 50% complete
  • Underpinning under M3 is 80% complete

M3:

  • Forming of the tower is now complete to L14
  • Window installation has commenced and completed till L5
  • Interior works in the parkade are 80% complete

M1 & M2:

  • Hoists have been removed, and balcony infills installed

Summer 2023

M4:

  • Detailed excavations at footings is 30% complete
  • Tower crane has been installed
  • Ramp leading to the excavation is being removed
  • Underpinning under M3 is 40% complete

M3:

  • 5 levels of the tower are structurally framed
  • Window installation has commenced on levels 2, 3 and 4
  • Podium tower crane has been removed
  • A climbing tower crane to the south of the tower is being erected, it will climb to the top of the tower
  • Construction hoist at the north end of the building has been installed
  • Civil works to create the Soho Avenue extension and Redmond Road are underway

M1 & M2:

  • Hoists are being removed and balcony infills are being installed
  • Interior and exterior amenities are nearly complete
  • Full occupancy of both buildings is scheduled for Q4 - 2023

Spring 2023

M4:

  • Bulk excavation is 90% complete
  • Construction work to underpin the tower is underway
  • The excavation for the building's footings is about to begin.

M3:

  • Podium structure is complete with columns and walls extending to the first residential tower floor
  • Finishes in the parkade continue with fire protection and masonry work
  • We are almost done with our podium crane and will soon remove it

M1 & M2:

  • M1 and M2 towers are now fully enclosed
  • Balcony railing installation is complete on both buildings except the hoist bay
  • Occupancy continues along with finishes up the towers

Winter 2023

M4:

  • Bulk excavation is well underway; 80% complete
  • Underpinning under M3 substructure is our next major milestone, targeted for Q1 2023

M3:

  • Podium structure is nearly complete with columns and walls extending to L8
  • Finishes in the parkade continue with fire protection and masonry work
  • Window installation expected to commence in Q2 of this year. This will allow us to commence interior finishes above grade

M1 & M2:

  • There is one level of windows left to install on the M2 tower
  • Balcony railing installation is complete on M1 and a few weeks from completion on M2
  • Occupancy to L29 is obtained on M1 with move ins happening every day
  • Interior finishes continue up to the roof of both towers

Fall 2022

M4:

  • Shoring system around the perimeter of the excavation is now complete
  • Bulk excavation is well underway; 40% complete
  • Underpinning under M3 substructure is our next major milestone, target for Q1, 2023

M3:

  • Podium structure is well underway, with columns and walls extending to L5
  • The climbing core system is being completed, this will allow the core of the tower to advance a floor ahead of the slabs

M1 & M2:

  • The structures have both topped off
  • The building maintenance unit is now installed on the roof
  • The mechanical penthouse is enclosed with windows
  • There are 5 levels of windows left to complete on the M1 tower
  • Balcony railing installation is complete up to level 55
  • Interior finishes have progressed through the podium and tower with completed suites up to L35

Summer 2022

M4:

  • Vertical drilling of the shoring system around the perimeter of the site has commenced
  • Bulk excavation of the middle of the site is well underway to expedite the excavation process

M3:

  • The parkade structure is complete
  • Portions of the mezzanine floor structure at the townhouses are underway
  • Fitzroy, the new road that separates M3 and M4, is being backfilled
  • Foundation waterproofing is complete

M1 & M2:

  • Down to the final concrete pours to complete the roof structures
  • Window installation is complete up to level 55
  • Balcony railing installation is complete up to level 48
  • Interior finishes have progressed through the podium and tower
  • Sidewalks and softscaping are well underway - about 50% complete

Spring 2022

M3:

  • Parking level 1 below grade is complete
  • Foundation waterproofing is approximately 90% complete
  • Ground floor forming is well underway

M1 & M2:

  • Walls and columns have progressed up to level 60
  • Roof topping off scheduled for this summer
  • Window installation is complete up to level 48
  • Balcony railing installation is complete up to level 41
  • Interior finishes have progressed through the podium and tower
  • Suites completed up to level 30
  • Streetscaping, curbs, and street lighting are in place
  • Sidewalks and softscaping to commence this summer, expected completion in the fall

Winter 2022

M3:

  • Parking level 2 below grade is 100% complete, with portion of P1 underway
  • Foundation waterproofing approx. 70% complete
  • Planning for ground floor slab is well under way

M1 & M2:

  • Walls and columns progressing to L53
  • Window installation is well underway and installations are complete to L41
  • Balcony railing installation is well underway and installed to L35
  • Interior finishes have progressed through the podium and well into the tower with completed suites up to L23
  • Boulevard/landscape works are set to resume after the frost comes out of the ground!

Fall 2021

M3:

  • Detailed excavation at footings approx. 95% complete
  • Underground drains are complete
  • Foundation waterproofing approx. 30% complete
  • Parkade well underway with portions of P5 being formed

M1 & M2:

  • Walls and columns progressing to L42
  • Window installation is well underway and installations are complete to L33
  • Balcony railing installation is well underway and installed to L26
  • Interior finishes have progressed through the podium and well into the tower with completed suites up to L11
  • Boulevard/landscape works underway with underground utility installations and relocations under way.

Summer 2021

M3:

  • Detailed excavation at footings approx. 75% complete
  • Underground drains are 80% complete
  • Foundation waterproofing approx. 20% complete
  • The first area of P7 + P6 parking slabs have been poured

M1 & M2:

  • Walls and columns progressing to L39
  • Window installation are advancing with installations complete to L29
  • Balcony railings have been installed to L23
  • Interior finishes have progressed through the podium and into the tower with completed suites up to L8
  • Civil works complete and internal roads complete to base coarse asphalt
  • Streetscape/landscape work expected to commence this Fall

Spring 2021

M3:

  • Bulk excavation is complete
  • Detailed excavation at the building core footings is underway
  • Crane bases for both tower cranes have been poured
  • Underground drainage contractor has mobilized with materials
  • Foundation waterproofing about to commence!

M1 & M2:

  • Walls and columns progressing to L27
  • Window installation is well underway and installations are complete to L18
  • Balcony railing installation is well underway and installed to L5
  • The underside of the balconies are being fitted with heating cables and a stucco soffit,complete to L13
  • Interior finishes have progressed through the podium and well into the tower
  • Interior roads and civil works are well underway, we are targeting to be complete withasphalt on the internal roads by late summer

Winter 2021

M3:

  • Bulk excavation is complete to P6
  • The bench that was left to facilitate the shoring, has now caught up to the bulk excavation
  • Wire mesh has been installed to protect the shale face
  • Stair tower down into the excavation is complete

M1 & M2:

  • Walls and columns progressing to L19
  • Window installation is well underway and installations are complete to L13
  • Interior finishes have commenced on progressing in the podium
  • Interior roads and civil works have commenced

Fall 2020

M3:

  • Bulk excavation in the center of the site is excavated to P4
  • The shoring system is complete with wood lagging
  • The bench around the perimeter of the site is in the process of being taken down to the same elevation as the bulk excavation

M1 & M2:

  • Walls and columns progressing to L10, which represent the typical floor!
  • Window installation is about to commence on the podium levels
  • Mechanical and electrical rooms are well underway
  • Parking garage finishes have commenced!

Summer 2020

M3:

  • Ground breaking ceremony has taken place with special guest Mayor Bonnie Crombie!
  • Vertical drilling of the shoring system is complete
  • Lagging around the perimeter of the site is now down to the first tie back elevation
  • The centre of the site is now bulked out to P3 level. At this elevation, we are well into shale!

M1 & M2:

  • With walls and columns progressing to L7, we are nearly on the typical floor, where we will begin to see increased productivity as the tower floor plate size is considerably smaller than the podium levels
  • Man and material hoists are now installed
  • Off-site materials are being fabricated, and window installation will commence in the fall
  • Major pieces of mechanical equipment have arrived to site and are being set in place

Spring 2020

M1 & M2:

  • The structure continues to progress and slabs and columns are now built to the 4th floor. These are the most complicated slabs on the project
  • Mechanical / electrical works and finishes commence below grade, along with fire protection
  • To continue with vertical works, its important to move personnel and materials up the building. As such, the hoist is planned to be installed in the summer months

Winter 2020

M1 & M2:

  • Parkade structure is complete
  • Concrete forming continues above grade with approx. 30% of 2nd floor slab complete
  • Mechanical and Electrical rough ins continuing
  • Masonry work in the parkade has commenced

Fall 2019

M1 & M2:

  • Construction of the parkade continues to advance back to grade
  • Sprinkler and plumbing installs at P5 commence
  • Electrical rough-ins are advancing to P4

Summer 2019

M1 & M2:

  • The suspended slabs within the parking structure are advancing up to P3
  • Foundation waterproofing to foundation walls continue to advance
  • Electrical and mechanical sleeving continues through the parkade structure

Spring 2019

M1 & M2:

  • Detailed excavation of footings continues
  • Tower cranes are installed
  • Underground drainage system at P5 / 4 levels are being installed
  • Footing installation ongoing
  • Foundation waterproofing being applied to rock face

Winter 2019

M1 & M2:

  • Shotcrete shoring system is complete
  • Excavation continues through shale
  • Wire screening is applied to excavation walls to protect works in the pit

Fall 2018

M1 & M2:

  • Excavation is well under way
  • Shoring system being installed to retain the land outside the property line

Summer 2018

M1 & M2:

  • Site prep has commenced on both M1 & M2 simultaneously
  • Clearing and grubbing of land
  • Set-up of perimeter hoarding
  • Temporary services brought to site